Gantt chart showing critical activities (Critical Path)
When creating a Gantt chart, users can choose automatic generation from bill-of-quantities items or manually enter the WBS structure and activities. With automatic generation, the software creates a Gantt chart for every work category and BOQ item.
Each activity can be edited further: change its name and duration, define dependencies between activities (SF, SS, FS, FF), add notes, enter the completion percentage, delays and other information.
The Gantt chart automatically highlights critical activities, i.e. activities with no time float on which project completion depends.
The Gantt chart can be exported to Excel or saved as a PNG image.
Activities and work categories can be moved up or down using drag and drop, or left and right to change their position in the hierarchical structure.
NOTE: Changes to the Gantt chart are not saved automatically. You must select the Save command. If you try to leave the page without saving, the application will offer to save the changes you have made.