Monitoring progress, deadlines and costs
Earned Value Analysis combines the planned value of work, the value of work actually performed and the costs incurred. It provides a single view of deviations from the planned schedule and budget, as well as a forecast of project performance through completion.
Key values
PV (Planned Value) – the planned value of work up to the selected point in time.
EV (Earned Value) – the earned value of completed work, calculated against the planned budget.
AC (Actual Cost) – the actual costs incurred for the completed work.
BAC (Budget at Completion) – the total planned project budget.
Performance indicators
CV = EV − AC – cost variance: a negative value indicates a cost overrun.
SV = EV − PV – schedule variance expressed in terms of work value: a negative value indicates a delay.
CPI = EV / AC – cost performance index.
SPI = EV / PV – schedule performance index.
EAC = BAC / CPI – an example of the estimated cost at completion, assuming the current cost performance continues.
Project monitoring example
Illustrative example; not a calculation for an actual project.
For a planned budget of €100,000, a planned value (PV) of €50,000, an earned value (EV) of €40,000 and actual costs (AC) of €45,000, the results are CV = −€5,000, SV = −€10,000, CPI ≈ 0.89 and SPI = 0.80. These indicators enable deviations to be identified promptly.